Rooppur nuclear power plant
Nuclear fuel loading starts at Rooppur power plant
The Rooppur Nuclear Power Plant officially began fuel loading into one of its two units yesterday afternoon, marking a historic moment in the nation’s energy sector.
29 April 2026, 00:00 AM
Rooppur begins fuel loading at unit-1 in landmark step
Significant leap in the nation’s technological capabilities, minister of science and information says
28 April 2026, 15:59 PM
Rooppur MD highlights safety measures, strict monitoring
Its multiple independent safety layers ensure that if one system fails, others immediately take over, Dr Zahedul Hasan says
28 April 2026, 15:08 PM
What fuel loading at Rooppur means for our energy future
The fuel loading process at the first unit of the Rooppur Nuclear Power Plant project is scheduled to commence today, April 28, in the presence of high-level representatives from Bangladesh, Russia, and the International Atomic Energy Agency.
28 April 2026, 08:00 AM
Bangladesh enters nuclear energy era
Bangladesh moves a step closer to achieving its long‑cherished goal of generating nuclear energy this afternoon with the start of fuel loading into the reactor core of unit‑1 at the Rooppur Nuclear Power Plant, marking the transition from the construction to the startup phase.
28 April 2026, 00:00 AM
Elation, unease at Rooppur
For residents of Rooppur, the nuclear power plant project was long seen as a pipe dream that remained unfulfilled for decades.
28 April 2026, 00:00 AM
Inception to fuel loading
1961: Then Pakistan government first took initiative for a nuclear power plant in Rooppur
28 April 2026, 00:00 AM
How power is generated at a nuclear plant
How nuclear energy and then electricity are produced is often feared as rocket science. The fact is that it is not that difficult to understand. It is, however, difficult to get it done safely and keep it under control.
28 April 2026, 00:00 AM
Shadow over future nuclear energy ambition
When Bangladesh signed its reciprocal trade agreement with the United States in February, headlines focused on garments and tariffs. Less noticed was a short clause in Article 4.3.
28 April 2026, 00:00 AM
First fuel loading at Rooppur power plant: A milestone explained
A closer look at how fuel is loaded, what follows next, and why the milestone matters
27 April 2026, 12:01 PM
Rooppur Nuclear Power Plant gets commissioning license for first unit's fuel loading
BAERA clears commissioning of first unit; fuel loading ceremony expected late April
16 April 2026, 23:41 PM
Bangladesh inks IAEA deal ahead of Rooppur fuel loading
Agreement aimed at ensuring peaceful and secure use of nuclear technology
21 March 2026, 10:57 AM
Rooppur power project seeks Tk 25,593cr cost hike
The cost of the Rooppur nuclear power plant is set to rise by Tk 25,593 crore, pushing the total outlay to Tk 138,685 crore and extending the completion deadline to 2028.
25 January 2026, 02:22 AM
Why nuclear intelligence is vital for Bangladesh
NUCINT bridges physical, cyber, and human dimensions of security.
7 November 2025, 03:10 AM
UN agency asks Rooppur to improve safety before opening
The International Atomic Energy Agency (IAEA) has recommended improvements in fire prevention and response, operational supervision, and equipment preservation at the Rooppur Nuclear Power Plant (RNPP) ahead of its commercial launch of the first unit.
28 August 2025, 18:00 PM
Govt moves to clear Rooppur dues to Russia after US waiver
Central bank seeks nod from Washington after Russia's reply
16 August 2025, 19:37 PM
8 more Rooppur Nuclear Power Plant staff suspended amid unrest
Last Thursday, 18 engineers were terminated in connection with the same unrest
14 May 2025, 10:40 AM
18 engineers dismissed from Rooppur nuclear project amid unrest
The dismissal includes 15 BSc engineers and three diploma engineers
11 May 2025, 07:17 AM
Rooppur Plant: NPCBL to finalise power purchase deal
The Nuclear Power Plant Company of Bangladesh Limited (NPCBL) has been given the responsibility for finalising the power purchase agreement with the Power Development Board (PDB) for selling electricity from the Rooppur Nuclear Power Plant.
2 May 2025, 19:38 PM
Rooppur power plant: Govt eyes quick completion
The total cost of the Rooppur Nuclear Power Plant project is Tk 1,14,225 crore, with the majority financed by Russia.
7 March 2025, 18:00 PM